Synopsis of Issues Raised:

The complainant alleges that UNDP is constructing a solid waste management facility on land contrary to local law, without the proper permits, and in a location that would have negative environmental impacts. The complainant further alleges economic harms will result to him, his family, and his workers when the new plant is operational. 

Intake Phase

Item Date Comments Documents
Step 1
Registration 2017-12-27

Initial Response Phase

Item Date Comments Documents
Step 2
Assessing Eligibility of Request 2018-01-08

Following an initial discussion with the Requester and gathering additional information and documentation from UNDP project staff, the case was determined eligible. 

Step 3
Assigning Responsibility for Response 2018-02-08

Following discussions between UNDP Lebanon and SRM-HQ, responsibility for the response and associated actions was shared between the two offices (CO and HQ).

Stakeholder Engagement Phase

Item Date Comments Documents
Step 4
UNDP Response 2018-02-08

UNDP facilitated a series of dialogues between stakeholders, including the Requester, representatives of the Municipality where the project was proposed, and the UNDP project staff. 

Step 5
Seeking Solution(s)
Step 6
Implementing Solution(s)

Monitoring Phase

Item Date Comments Documents
Step 7
Monitoring & Documenting Results

Final Phase

Item Date Comments Documents
Step 8
Closure and/or Referral of Case 2018-06-25

Unable to find a mutually agreeable solution, UNDP has suspended project activities in this location until an agreement is found.

The SRM case is closed.

Current case status

01.
Registration
Intake
Phase
02.
Assessing Eligibility of Request
03.
Assigning Responsibility for Response
Initial Response
Phase
04.
UNDP Response
05.
Seeking Solution(s)
06.
Implementing Solution(s)
Stakeholder Engagement
Phase
07.
Monitoring & Documenting Results
Monitoring
Phase
08.
Closure and/or Referral of Case
Final
Phase

Current case status

Intake
Phase
01.
Registration
Initial Response
Phase
02.
Assessing Eligibility of Request
03.
Assigning Responsibility for Response
Stakeholder Engagement
Phase
04.
UNDP Response
05.
Seeking Solution(s)
06.
Implementing Solution(s)
Monitoring
Phase
07.
Monitoring & Documenting Results
Final
Phase
08.
Closure and/or Referral of Case