Intake Phase
Item | Date | Comments | Documents |
---|---|---|---|
Step 1 | |||
Registration | 2015-08-07 |
Initial Response Phase
Item | Date | Comments | Documents |
---|---|---|---|
Step 2 | |||
Assessing Eligibility of Request | 2016-04-18 | Case determined to be eligible. |
|
Step 3 | |||
Assigning Responsibility for Response | UNDP India initiated a response to the complainants, with backstopping from SRM-HQ. |
Stakeholder Engagement Phase
Item | Date | Comments | Documents |
---|---|---|---|
Step 4 | |||
UNDP Response | 2016-08-16 | UNDP India facilitated a series of meetings and dialogues with stakeholders. |
|
Step 5 | |||
Seeking Solution(s) | 2017-11-03 | The dialogues resulted in a reformulation of the project document and implementation strategy, which were then formally endorsed by the State Government of Kerala. |
|
Step 6 | |||
Implementing Solution(s) | The revised project is now underway. |
Monitoring Phase
Item | Date | Comments | Documents |
---|---|---|---|
Step 7 | |||
Monitoring & Documenting Results | Ongoing. |
Final Phase
Item | Date | Comments | Documents |
---|---|---|---|
Step 8 | |||
Closure and/or Referral of Case |
Current case status
01.
Registration
IntakePhase
02.
Assessing Eligibility of Request
03.
Assigning Responsibility for Response
Initial ResponsePhase
04.
UNDP Response
05.
Seeking Solution(s)
06.
Implementing Solution(s)
Stakeholder EngagementPhase
07.
Monitoring & Documenting Results
MonitoringPhase
08.
Closure and/or Referral of Case
FinalPhase
Current case status
IntakePhase
01.
Registration
Initial ResponsePhase
02.
Assessing Eligibility of Request
03.
Assigning Responsibility for Response
Stakeholder EngagementPhase
04.
UNDP Response
05.
Seeking Solution(s)
06.
Implementing Solution(s)
MonitoringPhase
07.
Monitoring & Documenting Results
FinalPhase
08.
Closure and/or Referral of Case